(9-10-26) Tuesday night Coldwater School officials discussed major athletic facility upgrades at the Board of Education meeting.
Coldwater has faced financial issues and recently had to get approval of school district residents for additional funds.The district has been fighting that battle for several years.
- Coldwater Schools Inform Community Members On Tax Levy History
- A Look At The Coldwater Schools Future Financial Situation
- Coldwater Schools BOE To Discuss Income Tax Increase Proposal
- Coldwater Schools Withdraw Income Tax Proposal From November Ballot
- Coldwater Schools To Hold Special Meeting To Consider Tax Levy
- Coldwater BOE Looks To Approve Additional Traditional Income Tax
- Just In Case Levy Doesn’t Pass Today, Coldwater School Board Of Education To Meet On Wednesday
- Coldwater School Tax Levy Fails In Special Election
A major upgrade of the Coldwater gym (referred to as the Palace) will need the retractable bleachers to be replaced and the three courts to be refinished next summer (2027) for around $925,000.
The Coldwater track, that circles the varsity football field, looks to have approximately two years of use remaining. Depending on the condition of the subsurface, the cost be from $250,00-$300,000 or as much as $700,000-$800,000 to replace, according to school officials.
The gym upgrade has been included in the district’s 10-year-capital improvement plan.
The work schedule planned for the summer will be…press boxes will be removed from the gym between June 1-6, the bleachers will be replaced June 7-July 9, the entire gym floor will be refinished July 10-18, the press boxes will be returned July 19-25 and the gym will be reopened on July 26.
The funding of the projects have not been solidified, although the Coldwater Athletic Booster Club looks to be able to help.
Coldwater is the second Mercer County school district facing funding issues on athletic facilities. Celina Schools
RELATED:
- Celina City School Board Of Education Considers Selling Administration Building, Fieldhouse And Stadium
- Celina Schools BOE Vote On Future Athletic Facilities At A Special BOE Meeting
- EDITORIAL: Celina Schools Athletic Building Project Disappointments
- Celina City Schools Financial Concerns In New Building Project